Six project plans drawn as Gantt charts, each with the task list and dates behind it
A Gantt chart lists a project's tasks down the left and draws each one as a bar along a date axis, so you can see what happens when, what overlaps and what has to finish first. Below are six examples for different kinds of projects. Each one comes with its task list and dates, so you can copy the plan and change it to fit your own.
A small plan with one row per phase. Build and Testing overlap by a week, which a Gantt chart shows at a glance and a task list hides. The launch is a milestone: a single date rather than a stretch of work, drawn as a diamond.
| Task | Start | End |
|---|---|---|
| Research | Mar 2, 2026 | Mar 13, 2026 |
| Design | Mar 16, 2026 | Apr 3, 2026 |
| Build | Apr 6, 2026 | May 15, 2026 |
| Testing | May 11, 2026 | May 22, 2026 |
| Launch | May 26, 2026 | Milestone |
This is the plan our guides to making a Gantt chart in Excel, in Google Sheets, in PowerPoint and in Word build step by step.
Construction schedules are where Gantt charts earn their keep, because most of the work has to happen in order. Here the cabinets are ordered during planning, since they take six weeks to arrive, and each trade starts when the one before it finishes.
Planning Construction
| Task | Start | End |
|---|---|---|
| Design and measurements | Jan 4, 2027 | Jan 22, 2027 |
| Permits | Jan 25, 2027 | Feb 12, 2027 |
| Order cabinets and appliances | Jan 25, 2027 | Mar 5, 2027 |
| Demolition | Mar 8, 2027 | Mar 12, 2027 |
| Plumbing and electrical | Mar 15, 2027 | Mar 26, 2027 |
| Drywall and paint | Mar 29, 2027 | Apr 9, 2027 |
| Cabinets and countertops | Apr 12, 2027 | Apr 23, 2027 |
| Flooring and fixtures | Apr 26, 2027 | May 5, 2027 |
| Final inspection | May 7, 2027 | Milestone |
The long cabinet order is the bar to watch. It has five weeks of slack before the cabinets go in, but a delay longer than that pushes back the install and everything after it. For more on this kind of plan, see our guide to construction timelines.
Two teams, one date. Coloring the bars by team shows who is busy when, and the launch day milestone shows which work has to be finished before it and which carries on after.
Product Marketing
| Task | Start | End |
|---|---|---|
| Beta program | Feb 1, 2027 | Mar 12, 2027 |
| Pricing and packaging | Feb 15, 2027 | Mar 5, 2027 |
| Launch page and copy | Mar 1, 2027 | Mar 26, 2027 |
| Press outreach | Mar 15, 2027 | Apr 9, 2027 |
| Email campaign | Mar 29, 2027 | Apr 16, 2027 |
| Launch day | Apr 13, 2027 | Milestone |
| Post-launch review | Apr 19, 2027 | Apr 30, 2027 |
The email campaign runs past launch day on purpose: the announcement goes out on the day and the follow-ups after it.
An event plan runs backward from a date that cannot move. Over nine months the bars are long and overlap heavily, so the chart is less about sequence and more about how many things are in flight at once.
| Task | Start | End |
|---|---|---|
| Set budget and goals | Jan 4, 2027 | Jan 29, 2027 |
| Book venue | Feb 1, 2027 | Mar 12, 2027 |
| Confirm speakers | Mar 1, 2027 | May 28, 2027 |
| Sponsorship sales | Mar 15, 2027 | Jul 30, 2027 |
| Promotion | May 17, 2027 | Sep 3, 2027 |
| Registration open | Jun 1, 2027 | Sep 10, 2027 |
| Catering and AV | Jul 5, 2027 | Aug 27, 2027 |
| Conference | Sep 14, 2027 | Sep 16, 2027 |
July is the crunch, with four tasks in flight at once. Our guide to event planning timelines covers how to work backward from the event date.
A year-long plan for one person. Several stages overlap, because in practice you begin analyzing while data is still coming in and begin writing before the analysis is done.
| Task | Start | End |
|---|---|---|
| Literature review | Jan 11, 2027 | Mar 26, 2027 |
| Proposal and ethics approval | Mar 1, 2027 | Apr 30, 2027 |
| Data collection | May 3, 2027 | Jul 30, 2027 |
| Analysis | Jul 5, 2027 | Sep 24, 2027 |
| Writing | Sep 6, 2027 | Nov 19, 2027 |
| Revisions | Nov 22, 2027 | Dec 10, 2027 |
| Submission | Dec 15, 2027 | Milestone |
Data collection cannot start until approval comes through, which makes the proposal the task most likely to delay the rest. See our guides to research project timelines and PhD timelines for more detail.
Three two-week sprints, with documentation and testing starting during the last one. The two milestones mark the dates people outside the team care about: when the beta goes out and when the release ships.
Planning Development Release
| Task | Start | End |
|---|---|---|
| Requirements | Mar 1, 2027 | Mar 12, 2027 |
| Sprint 1 | Mar 15, 2027 | Mar 26, 2027 |
| Sprint 2 | Mar 29, 2027 | Apr 9, 2027 |
| Sprint 3 | Apr 12, 2027 | Apr 23, 2027 |
| Documentation | Apr 12, 2027 | May 7, 2027 |
| QA and bug fixes | Apr 19, 2027 | May 7, 2027 |
| Beta release | Apr 26, 2027 | Milestone |
| Release | May 11, 2027 | Milestone |
Our guide to software project timelines goes deeper on planning a release.
New to planning one? See what is a Gantt chart for the parts these examples share, and our guide to how to make a Gantt chart for the steps that come before any tool. You can build any of these in a spreadsheet with a stacked bar chart, and the guides linked under the website launch example show how. It works, but every bar is placed by a formula you maintain.
In Preceden you type the tasks and their dates, and it draws the chart. Create a timeline with the Gantt Chart template, then add each task from the example you want to start from. Group tasks into layers to color them by phase or team, make a task start when another one ends, shade a bar by its percent complete, and mark key dates as milestones. Our guide to creating Gantt charts covers each of these.
You can also have Preceden draft the plan for you. Type a project with the word Gantt in it, such as "Gantt chart for a kitchen remodel", into the generator on our [homepage](/), then edit the tasks and dates it suggests.
Every example on this page has 10 tasks or fewer, so each one fits on our free plan, which allows up to 10 events per timeline. Preceden is built for communicating a schedule rather than running the work, so you can't assign tasks to people or calculate a critical path in it.
Not sure whether your project needs a Gantt chart at all? See Gantt chart vs timeline for how to choose.