Word has no Gantt chart type, but you can build one from a stacked bar chart or draw one with a table and shaded cells. This guide walks through both, then shows how to make the chart in Preceden and insert it into your document as an image instead.
Start with one row per task, with its start date and how many days it takes. Here is a small website launch plan we'll use as the example:
| Task | Start | Duration |
|---|---|---|
| Research | 3/2/2026 | 11 |
| Design | 3/16/2026 | 18 |
| Build | 4/6/2026 | 39 |
| Testing | 5/11/2026 | 11 |
| Launch | 5/26/2026 | 1 |
The duration is the number of days from a task's start date to its end date, so Research runs from March 2 to March 13.
This is the classic method. Each task gets two bars stacked end to end: an invisible one that pushes the visible bar out to the task's start date, and a visible one as long as the task.
The bars that remain are your Gantt chart, but they probably sit at the far right of a date axis that starts in 1900. Word stores the chart's dates as numbers of days, as Excel does, so click the dates along the axis and, under Format Axis, set the Minimum bound to the number for your first start date. For 3/2/2026 that is 46083. To find yours, enter a date in an empty cell of the chart's spreadsheet and format it as General.
To change a date later, right-click the chart and choose Edit Data. The chart can't show dependencies between tasks or how much of a task is complete.
If you already have the chart in Excel, you can copy it there and paste it into your document instead. Our guide to making a Gantt chart in Excel walks through the same method in Excel itself.
This method fits a Gantt chart into the flow of a document, such as a project proposal, at the cost of shading the cells by hand.
The shaded cells aren't tied to any dates, so when the schedule changes, you have to shade and clear the cells yourself. Each cell is a whole week or month, so a task that starts midweek still fills the full cell.
Looking for a Word Gantt chart template? This table can become your own. Once the headings and colors look right, clear out the task names and shading, then click File, then Save As, and choose Word Template as the file type. Your next plan can start from it.
If your plan has more than a handful of tasks, or you need dependencies, you can make the Gantt chart in Preceden and put it in your document as a picture.
Create a new timeline with the Gantt Chart layout, then add your tasks with their start and end dates. You can type them in one at a time, use the Bulk Editor, which works like a spreadsheet, or import an Excel or CSV file as our CSV and Excel import guide describes. Importing is part of our paid plans; on the free plan you can create timelines with up to 10 events each.
Once the tasks are in, you can make a task start when another one ends, shade each bar by its percent complete and add milestones. Our guide to creating Gantt charts covers each of these. Preceden is built for communicating a schedule rather than running the work, so you can't assign tasks to people or calculate a critical path in it.
To get the image, click Share above your timeline, choose Image and click Download Now to save it as a PNG. Then in Word, click Insert, then Pictures, and choose the file. The picture is a snapshot of your chart, so when the plan changes, update it in Preceden and insert the new image in place of the old one. Our guide to printing and exporting your timeline covers the image settings and the PDF option.
Making a timeline of dates rather than a schedule of tasks? See our guide to creating a timeline in Word. Building the chart for a presentation instead? See our guide to making a Gantt chart in PowerPoint.