Hoover Dam is a concrete arch-gravity dam on the Colorado River, located on the border between Nevada and Arizona. Built during the Great Depression, it was the tallest dam in the world at the time of its completion and provides hydroelectric power, flood control, and water storage for millions of people. More Less
1902
% complete
Following the creation of the United States Reclamation Service in 1902, engineers began surveying the Colorado River basin to identify sites for dams that could control flooding, store water, and generate hydroelectric power for the arid American Southwest.
Image source: Bureau of Reclamation
1905 - 1907
% complete
The Colorado River breached irrigation canals and flowed into the Salton Sink for nearly two years, creating the Salton Sea and devastating farmland in the Imperial Valley. The disaster underscored the urgent need to control the unpredictable river.
Image source: Salton Sea
Nov 24, 1922
% complete
Representatives of seven western states met at Santa Fe, New Mexico, to divide the waters of the Colorado River between its Upper and Lower Basins. The compact was a prerequisite for congressional approval of a major dam project on the river.
Image source: Colorado River Compact
Dec 21, 1928
% complete
President Calvin Coolidge signed the Boulder Canyon Project Act, authorizing the construction of a dam on the Colorado River. The act followed years of debate among seven basin states and the negotiation of the Colorado River Compact of 1922.
Image source: Hoover Dam
1931
% complete
A consortium of six major construction firms from the West, known as Six Companies Inc., won the federal contract with a bid of about $48.9 million, then the largest contract ever awarded by the federal government.
Image source: Six Companies
Apr 20, 1931
% complete
After winning the bid, Six Companies began work on the massive concrete arch-gravity dam in Black Canyon on the Colorado River, launching one of the largest public works projects in American history during the Great Depression.
Oct 1932 - Jun 1933
% complete
Upstream and downstream cofferdams were constructed to seal off the work area after the diversion tunnels were finished, enabling excavation of millions of cubic yards of mud, silt, and loose rock down to bedrock.
Nov 14, 1932
% complete
Workers blasted four large diversion tunnels through the canyon walls to reroute the Colorado River around the dam site, allowing crews to begin excavating the riverbed and building the dam's foundation on dry rock.
Jun 6, 1933
% complete
The first bucket of concrete was placed into the dam's foundation. Engineers devised an innovative system of interlocking columns of concrete blocks embedded with cooling pipes to dissipate heat and allow the enormous mass to cure properly.
1931
% complete
The federal government built Boulder City, Nevada, as a planned community to house thousands of dam workers and their families, providing housing, schools, and services in the harsh desert environment near the construction site.
Image source: Boulder City, Nevada
1931 - 1936
% complete
Officially, 112 deaths were attributed to construction of the dam, caused by falls, blasts, machinery, and heat. Harsh working conditions, including summer temperatures exceeding 120 degrees Fahrenheit, made the project extraordinarily dangerous.
Aug 7, 1931 - Aug 9, 1931
% complete
Hundreds of workers went on strike to protest wage cuts, unsafe conditions, and poor treatment by Six Companies. The strike collapsed within days when company officials refused concessions and threatened to replace the strikers.
1931 - 1933
% complete
Daring workers called high scalers dangled from ropes hundreds of feet above the canyon floor, drilling and blasting loose rock off the canyon walls so concrete could bond securely to the rock. Their feats became legendary among dam workers.
1933 - 1935
% complete
Massive steel penstocks, some 30 feet in diameter, were fabricated and installed to carry water from intake towers to the turbines in the power plant at the base of the dam, a feat of heavy fabrication for its time.
1933 - 1935
% complete
Engineers embedded more than 582 miles of steel pipe through which chilled water circulated, cooling the concrete. Without this system, the dam would have taken over a century to cool naturally, making it one of the era's great engineering innovations.
1935
% complete
Architect Gordon Kaufmann applied Art Deco styling to the dam, its towers, and terraces, while sculptor Oskar Hansen created the Winged Figures of the Republic monument, blending artistry with monumental engineering.
1935
% complete
Four towering concrete intake structures were completed on the upstream face of the dam, each fitted with massive cylindrical gatehouses that control the flow of water into the penstocks feeding the power plant.
Aug 1941
% complete
Rising floodwaters forced operators to use the dam's spillways for the first time. The tests revealed cavitation damage in the spillway tunnels, leading to engineering studies and repairs that improved understanding of high-velocity water flow.
Feb 1, 1935
% complete
With the diversion tunnels closed, water began backing up behind the dam, forming Lake Mead, the largest reservoir in the United States by volume when full, stretching over 100 miles up the Colorado River.
Image source: Lake Mead
Apr 30, 1935
% complete
Sculptor Oskar J.W. Hansen's twin bronze winged figures were dedicated at the Nevada abutment, standing as a memorial to the workers who built the dam and symbolizing the nation's optimism and strength.
May 29, 1935
% complete
The last bucket of concrete was placed, topping out the dam two years ahead of schedule. In total, about 4.36 million cubic yards of concrete had been used, enough to pave a road across the continental United States.
Sep 30, 1935
% complete
Although Secretary of the Interior Ray Lyman Wilbur had named it Hoover Dam in 1930, political controversy led officials to call it Boulder Dam for several years. Congress permanently restored the name Hoover Dam in 1947.
Sep 30, 1935
% complete
President Roosevelt delivered a dedication speech before a crowd of thousands, hailing the dam as a triumph of engineering and a symbol of hope during the Great Depression. The event marked the formal completion of the project.
Oct 26, 1936
% complete
The first generator went online, delivering hydroelectric power to Southern California and later Arizona and Nevada. At its completion, Hoover Dam was the largest hydroelectric facility in the world.
Apr 30, 1947
% complete
After years of the dam being referred to as Boulder Dam, President Harry Truman signed a resolution officially designating the structure as Hoover Dam, honoring the president who authorized the project as commerce secretary.
Aug 20, 1985
% complete
The dam was designated a National Historic Civil Engineering Landmark and listed on the National Register of Historic Places, recognizing its significance as a masterpiece of engineering and a defining achievement of the New Deal era.
1995
% complete
A modern visitor center opened, offering exhibits, observation decks, and guided tours. Today the dam attracts nearly one million visitors annually, remaining one of the most popular tourist destinations in the American Southwest.
2000 - 2022
% complete
A prolonged drought in the Colorado River basin caused Lake Mead's water levels to fall dramatically, exposing long-submerged features and prompting concerns about hydropower capacity and water supplies for millions of people.
Oct 19, 2010
% complete
The Hoover Dam Bypass Bridge opened, carrying U.S. Route 93 traffic across Black Canyon just downstream of the dam. It relieved the dam's roadway of through traffic and became the first concrete-steel composite arch bridge built in the United States.
Image source: Mike O'Callaghan–Pat Tillman Memorial Bridge
2021
% complete
More than eight decades after completion, Hoover Dam continues to produce roughly 4 billion kilowatt-hours of electricity per year, serving about 1.3 million people and standing as an enduring icon of American engineering.
Or browse the full history timeline directory, with more than 2,000 topics.
This Hoover Dam timeline was generated with the help of AI, using information found on the internet.
We work hard to keep these timelines accurate, but mistakes do get through. If you spot one, email us at [email protected] and we'll fix it for future visitors.
Generate yours with AI or build it from scratch, for free.
Export your timeline, add your own events, edit or remove AI-generated events, and much more
No credit card required.
Cancel anytime.
Cancel anytime.
You can create an unlimited number of timelines with up to 10 events on each one, customize how they look, export them to PDF, PNG, PowerPoint, CSV, and Excel, and share them with a link. Paid plans raise the event limit and add features like spreadsheet imports and collaborators.
Yes. You can cancel your subscription from your account page at any time, and you will not be charged again. Your subscription stays active for the rest of the period you already paid for.
Yes. We will email you a reminder before the annual renewal, and we will also email you a receipt.
Yes. You can email us within 15 days of any payment, and we will issue you a full refund.
Check out our pricing docs or send us an email anytime: [email protected].