The Artemis Program is NASA's ambitious initiative to return humans to the Moon and establish a sustainable lunar presence, serving as a stepping stone for future crewed missions to Mars. Named after the Greek goddess of the Moon and twin sister of Apollo, the program includes the Space Launch System (SLS) rocket, the Orion spacecraft, and international partnerships through the Artemis Accords. More Less
2005
% complete
Originally legislated by the NASA Authorization Act of 2005, as the retirement of the Space Shuttle drew near, the Constellation program included the development of the Ares I and Ares V rockets along with the Orion spacecraft.
2009
% complete
The committee concluded that the Constellation program was massively underfunded and that a 2020 Moon landing was impossible.
May 2009
% complete
In May 2009, US president Barack Obama established the Augustine Committee to take into account several objectives including support for the International Space Station, development of missions beyond low Earth orbit (including the Moon, Mars, and near-Earth objects), and use of the commercial space industry within defined budget limits.
Apr 15, 2010
% complete
On April 15, 2010, President Obama spoke at the Kennedy Space Center, announcing the administration's plans for NASA and canceling the non-Orion elements of Constellation, saying that the program was not viable. He instead proposed US$6 billion in additional funding and called for the development of a new heavy-lift rocket program to be ready for construction by 2015 with crewed missions to Mars orbit by the mid-2030s.
Oct 11, 2010
% complete
On October 11, 2010, President Obama signed into law the NASA Authorization Act of 2010, which included requirements for the immediate development of the SLS rocket and the Orion spacecraft to support missions beyond low Earth orbit starting in 2016, while making use of the workforce, assets, and capabilities of the Space Shuttle program, Constellation program, and other NASA programs.
Jun 30, 2017
% complete
On June 30, 2017, President Donald Trump signed an executive order to re-establish the National Space Council, chaired by Vice President Mike Pence.
Dec 11, 2017
% complete
The Artemis program was formally established via Space Policy Directive-1 in 2017 by President Donald Trump. On December 11, 2017, President Trump signed Space Policy Directive 1, calling for a US-led program for a human return to the Moon, followed by missions to Mars and beyond.
Mar 26, 2019
% complete
On March 26, 2019, Pence announced that NASA's Moon landing goal would be accelerated by four years with a planned landing in 2024.
May 16, 2019
% complete
On May 16, 2019, NASA Administrator Jim Bridenstine announced that the new program would be named Artemis, after the goddess of the Moon in Greek mythology who is the twin sister of Apollo, after which NASA's 1960s moon landing program was named. Mars missions by the 2030s were still intended as of May 2019.
Feb 2020
% complete
In February 2020, the White House requested a funding increase of 12% to cover the Artemis program as part of its fiscal year 2021 budget. However, in July 2020, the House Appropriations Committee rejected the White House's requested funding increase.
Feb 4, 2021
% complete
On February 4, 2021, the Biden administration endorsed the Artemis program. However, throughout February 2021, Acting Administrator of NASA Steve Jurczyk reiterated budget concerns when asked about the project's schedule, clarifying that 'The 2024 lunar landing goal may no longer be a realistic target.'
Nov 15, 2021
% complete
On November 15, 2021, an audit of NASA's Office of Inspector General estimated the true cost of the Artemis program at about $93 billion until 2025.
May 6, 2010
% complete
The Pad Abort-1 test on May 6, 2010, demonstrated Orion's launch abort system, proving it could pull a crew module away from a rocket during a pad emergency.
Dec 5, 2014
% complete
In between abort tests, a prototype Orion crew module flew on Exploration Flight Test-1 on December 5, 2014 atop a Delta IV Heavy rocket. Following the cancellation of the Constellation program in 2010, Orion had been heavily redesigned for use in NASA's Journey to Mars initiative, later named Moon to Mars.
May 2019
% complete
In May 2019, the plan was for components of a crewed lunar lander to be deployed to the Gateway on commercial launchers before the arrival of the first crewed mission, Artemis III. As late as mid-2019, NASA also considered use of Delta IV Heavy and Falcon Heavy to launch a crewed Orion mission given SLS delays.
Jul 2019
% complete
The European Ariane 6 has been proposed to be part of the program in July 2019.
Jul 2, 2019
% complete
The Ascent Abort-2 test on July 2, 2019, proved that the system could pull a crew module away during launch at the point of maximum aerodynamic pressure (max q).
Apr 2020
% complete
In April 2020, NASA awarded funding to Blue Origin, Dynetics, and SpaceX for 10-month-long preliminary design studies for the HLS. In addition, NASA awarded two rounds of separate contracts in May 2019 and September 2021, on aspects of the HLS to encourage alternative designs, separately from the initial HLS development effort.
Apr 16, 2021
% complete
On April 16, 2021, NASA contracted SpaceX to develop, manufacture, and fly two lunar landing flights with the Starship HLS lunar lander. The SpaceX Starship is also qualified to be bid for Commercial Lunar Payload Services (CLPS) launches, and in 2021 was the winning NASA bid for a crewed lunar landing.
Mar 2022
% complete
NASA announced in March 2022 that it was developing new sustainability rules and pursuing both a Starship HLS upgrade (an option under the initial SpaceX contract) and new competing alternative designs.
2024
% complete
In 2024, SpaceX's Jennifer Jensen stated on a call that Starship HLS will require ten launches.
2027
% complete
The Power and Propulsion Element (PPE) module and the Habitation and Logistics Outpost (HALO) of the Gateway, which were previously planned for the SLS Block 1B, were then planned to fly together on a Falcon Heavy in 2027. Previously, according to early mission concepts outlined by NASA in May 2020 and refined by the HLS contract award in July 2021, primary Earth-launch vehicles planned include the NASA Space Launch System for the Orion vehicle, the Falcon Heavy for various components of the Lunar Gateway, and the Starship HLS configuration for delivery of the HLS vehicle.
Oct 2019
% complete
The Artemis program uses two types of space suit first unveiled in October 2019: the Orion Crew Survival System (OCSS) for launch and entry, and a next-generation extravehicular mobility unit (EMU) for lunar surface operations.
Feb 2020
% complete
In February 2020, NASA released two requests for information regarding both a crewed and uncrewed unpressurized surface rover. In July 2020, NASA established a program office for the rover at the Johnson Space Center in Houston.
2022
% complete
Development of NASA's Exploration Extravehicular Mobility Unit (xEMU) encountered delays; a 2021 audit by the NASA Office of Inspector General found it would not be ready before 2025. In response, NASA shifted to a commercial services model and selected Axiom Space and Collins Aerospace in 2022 to develop lunar spacesuits. Collins later withdrew from the contract in 2024.
2022
% complete
In 2022, NASA identified 13 candidate regions near the lunar South Pole for initial landing and inspection missions.
Oct 1, 2023 - Dec 31, 2023
% complete
The Italian Space Agency signed a contract with Thales Alenia Space in late 2023 for the Multi Purpose Habitation module, which may become the second module for the Artemis Base Camp.
2024
% complete
Development has since focused on the Axiom Extravehicular Mobility Unit (AxEMU), which entered critical design review and testing in 2024. By February 2026, the suit had passed internal reviews and was undergoing further evaluation by NASA, with assembly of the first flight unit underway following pressurized and underwater mobility testing at the Neutral Buoyancy Laboratory. NASA plans an in-space demonstration aboard the International Space Station in 2027.
Apr 3, 2024
% complete
On April 3, 2024, NASA announced that Intuitive Machines, Lunar Outpost and Venturi Astrolab are the three companies developing the LTV in a 12-month feasibility and demo phase. A source selection statement by NASA provided further details on cost and overall feasibility on April 9, 2024.
Apr 9, 2024
% complete
On April 9, 2024, it was announced that JAXA and NASA had signed an agreement stipulating that Japan would join the pressurized rover collaboration venture and would design, develop, and operate a rover for crewed and uncrewed exploration of the Moon.
Nov 16, 2022
% complete
Artemis I (November 16, 2022) was the first uncrewed test flight of the SLS, Orion, and ESM. The uncrewed Artemis I mission sent an Orion spacecraft to lunar orbit in 2022, carrying mannequins and robotic payloads. Originally scheduled for late 2016, it was delayed repeatedly, eventually for late 2021, then pushed back to August 29, 2022; in October 2022, NASA launch managers decided on a November date, which was again slightly delayed due to preparation and weather.
Apr 1, 2026
% complete
Artemis II sent four astronauts on a lunar flyby in 2026, becoming the only crewed flight beyond low Earth orbit not part of the Apollo program. The crewed Artemis II (lunar fly-by) mission flew on April 1, 2026, and was the first crewed test flight of SLS and Orion.
Oct 1, 2027 - Dec 31, 2027
% complete
Artemis III, scheduled for late 2027, is planned to test an HLS lunar lander in Earth orbit. It is planned to be the second crewed Artemis mission. As of February 2020, a lunar stay during a Phase 1 Artemis mission will be about seven days and will have five extravehicular activities (EVA). In the 2020 flight manifest it was later referred to as the 'Mobile Habitat'.
Jan 1, 2028 - Mar 31, 2028
% complete
Artemis IV, targeted for 2028, is planned to be the first crewed lunar landing since Apollo, and the first American crewed lunar landing since Apollo 17 in December 1972. Other designs from 2019 envisioned its lander being launched from an SLS Block 1B as a single unit and landing directly on the surface; launch plans as of February 2020 showed that landing it on the surface would be similar to the HLS.
Oct 1, 2028 - Dec 31, 2028
% complete
Artemis V (late 2028) is planned to be the second crewed lunar landing. Beginning with Artemis V, scheduled for no earlier than late 2028, NASA intends yearly lunar landings to develop a permanent lunar base, as a step toward human missions to deeper space.
Or browse the full history timeline directory, with more than 2,000 topics.
This Artemis Program timeline was generated with the help of AI, using information found on the internet.
We work hard to keep these timelines accurate, but mistakes do get through. If you spot one, email us at [email protected] and we'll fix it for future visitors.
Generate yours with AI or build it from scratch, for free.
Export your timeline, add your own events, edit or remove AI-generated events, and much more
No credit card required.
Cancel anytime.
Cancel anytime.
You can create an unlimited number of timelines with up to 10 events on each one, customize how they look, export them to PDF, PNG, PowerPoint, CSV, and Excel, and share them with a link. Paid plans raise the event limit and add features like spreadsheet imports and collaborators.
Yes. You can cancel your subscription from your account page at any time, and you will not be charged again. Your subscription stays active for the rest of the period you already paid for.
Yes. We will email you a reminder before the annual renewal, and we will also email you a receipt.
Yes. You can email us within 15 days of any payment, and we will issue you a full refund.
Check out our pricing docs or send us an email anytime: [email protected].